Zimmerberg Base Tunnel

The Zimmerberg Base Tunnel (ZBT) is a railway tunnel under the Zimmerberg mountains in Switzerland. Phase I of the tunnel was opened to traffic during April 2003.

Zimmerberg Base Tunnel
Overview
LineGotthard Line
LocationZürich, Switzerland
Coordinates47°19′40″N 8°31′52″E / 47.3277°N 8.5312°E / 47.3277; 8.5312
StatusActive since 2003
SystemSwiss Federal Railways (SBB CFF FFS)
StartZürich
EndThalwil
Operation
OpenedApril 2003[1]
OwnerSBB Infrastructure
OperatorSBB CFF FFS
TrafficRailway
CharacterPassenger and freight
Technical
Length9.4 km (5.8 mi)[2]
No. of tracks2[2]
Track gauge1,435 mm (4 ft 8+12 in) (standard gauge)
Electrified15 kV 16.7 Hz
Operating speed160 km/h (99 mph)
The NRLA project (Gotthard Base Tunnel and Zimmerberg Base Tunnel) is the centerpiece of the Central European rail network.

The ZBT has been divided into two phases of work; as of 2024, only Phase I is operational while Phase II remains in the planning and preparation stages. Zimmerberg I is about 10 km long; it links Zürich with Thalwil, bypassing a section of the Lake Zürich left-bank railway line, which allows rail traffic to traverse the mountains more efficiently.

Phase I

edit

During the 1990s, Switzerland embarked upon a major programme of modernization and improvements across its railway infrastructure.[3] The NRLA initiative sought to provide better alternatives to the steep mountain railways across Gotthard, Ceneri and Lötschberg through the construction of a number of base-level tunnels that enabled trains to more rapidly and efficiently traverse the Swiss Alps. The Zimmerberg Base Tunnel (ZBT) was one such tunnel constructed under the initiative.[4]

Phase I of the Zimmerberg Base Tunnel is a major feature of the route between Zürich and Thalwil. The tunnel was the longest double-track tunnel to have been constructed by Switzerland in over 100 years, a milestone in Swiss railway infrastructure.[5] The tunnel was designed to accommodate high speed transit, with trains traversing at peak speeds of up to 200 km/h. The projected cost of the 10.7 km Phase I section was reportedly 820 million Swiss francs. Construction of the tunnel commenced in September 1997.[5][6]

The local geography and location of the tunnel posed some challenges to the construction effort, such as the need to avoid impacting nearby urban development, as well as little cover being available at key areas.[7][8] Boring operations through the rock incorporated both the use of a tunnel boring machine and conventional techniques, such as blasting, soil injection, and pipe arches amongst other auxiliary construction measures intended to reduce the risk of excessive settlement.[7] Approximately 315 meters of the tunnel's length features a continuous grouted ceiling, which was done to reduce deformation and permeability as well as a potential loss of cover. This was created by injecting a precise mixture of cement and slurry via pressurized grouting pipes across 120,000 valves; areas were tested for potential weaknesses and promptly re-grouted where appropriate.[8]

From an early stage of the project, the tunnel's opening was projected for June 2003.[5] This _target was met on time.[8]

Phase II

edit

The proposed Phase II of the Zimmerberg Base Tunnel is one element of the wider Rail 2030 programme, which has an overall projected budget of 21 billion Swiss francs.[9] However, during 2010, it was reported that further work on the project had been put on hold indefinitely. At the time, work was underway on multiple other base tunnels, including the Ceneri Base Tunnel and the Gotthard Base Tunnel.[10]

If it is built as per the original plans, Phase II of the tunnel will bring its length to about 20 km, and will link Zürich with Zug. Even following its completion, it is planned to retain the intermediate exit to Thalwil, which would still be used by passenger and freight trains going to Chur as well as by international trains to Austria. Until Phase II is completed, capacity and speeds both remain heavily constrained by traditional routes; the Swiss Federal parliament has voted to include the work in its long term expansion plan for 2030–2035.[11][12]

See also

edit

References

edit
  1. ^ "Gotthard Base Tunnel". railway-technology.com. Retrieved 9 June 2020.
  2. ^ a b "Project data – raw construction Gotthard Base Tunnel" (PDF). Lucerne, Switzerland: AlpTransit Gotthard AG. 1 June 2016. Retrieved 15 December 2016.
  3. ^ Zbinden, Peter (2000). "New Gotthard Rail Link: a Technical Challenge". Structural Engineering International. 10 (1): 28–29. doi:10.2749/101686600780620937. eISSN 1683-0350. ISSN 1016-8664. S2CID 110985378. Retrieved 23 March 2018.
  4. ^ Zuber, Peter (July 1997). "The AlpTransit scheme: New railway lines in base tunnels under the Swiss Alps". Tunnelling and Underground Space Technology. 12 (3): 357–360. doi:10.1016/S0886-7798(97)00029-1. ISSN 0886-7798.
  5. ^ a b c Bosshard, Martin and Matter, Jürg (2000). "How the Zimmerberg-Base Tunnel is Being Built in the City of Zurich". IABSE Congress Report. 16: 782–789. doi:10.2749/222137900796356080. ISBN 3-85748-101-3.{{cite journal}}: CS1 maint: multiple names: authors list (link)
  6. ^ Amberg, F (14 February 2014). "Gotthard Basetunnel: Aspects of Long Tunnels" (PDF). indico.cern.ch.
  7. ^ a b "SBB Zimmerberg base tunnel". Basler & Hofmann. Archived from the original on 14 June 2021. Retrieved 9 June 2020.
  8. ^ a b c Matter, J.; Portner, J. (July 2004). "Successful grouting for the Zimmerberg Base Tunnel". Tunnelling and Underground Space Technology. Underground Space for Sustainable Urban Development. Proceedings of the 30th ITA-AITES World Tunnel Congress Singapore, 22–27 May 2004. 19 (4–5). trid.trb.org. ISSN 0886-7798. Retrieved 10 June 2020.
  9. ^ "Zimmerberg Base Tunnel". Archived from the original on 20 August 2010. Retrieved 3 May 2010. Official project site
  10. ^ Booth, Martina (29 April 2010). "Gotthard: A titanic tunnel". newcivilengineer.com.
  11. ^ Raaflaub, Christian (1 June 2017). "Swiss obsession with tunnels continues". swissinfo.ch.
  12. ^ Vosman, Quintus (14 November 2019). "Swiss adopt SFr 13bn plan to increase rail capacity by 2035". railjournal.com.
edit
  NODES
INTERN 2
Note 1
Project 9